Most rural charging projects start from the grid side: apply for a big feed, wait, and hope. The maker took the opposite route at the farm in Vörå, Finland, starting from a small and affordable connection and planning to reach a 400 kW peak by buffering that limited grid power with stationary battery storage, paired with an expanded solar array. The maker says a direct 700 A utility connection was prohibitively expensive and would have taken over five years; in my view that makes the buffered route the only realistic path.
The site so far has an exterior electrical cabinet with metering and breakers, two wall-mounted 22 kW AC chargers, and rooftop photovoltaic panels on two red wooden buildings. While the permanent hardware is still to come, a portable Kempower T-Series mobile DC charger is serving the site. Getting even the modest connection took a year and a half and cost around €6,500, which gives a sense of how slow rural grid work can be.
Testing has already happened with a Volvo EV, charging at 40 kW, measured as 63 A at 400 V, and the Kempower unit supports both CCS2 and CHAdeMO at that rate.
The big unfinished piece is the peak output itself: the 400 kW figure is an intention, not a delivered result. The stages ahead include civil groundworks, underground DC cabling, concrete foundations and the Kempower Satellite dispenser installations. How the stationary storage will be sized to actually hit that peak is still an open question.
Project by Dala's EV Repair. Watch it on their YouTube channel: