Finally got my permit approved and the inspector signed off on my rooftop array last week. Feels good to have it done myself, but now that the dust has settled I keep second guessing some of the choices I made and I'm curious how other people handled the same stuff.
The big one for me was conduit runs. I put everything on the outside of the roof and down the fascia because it was way easier to work with, but I see a lot of talk about flush mounting and hiding lines. Also wondering where people landed on rapid shutdown. My inspector wanted it, no arguments there, but the wiring under the panels is the part I keep looking at and wondering if I should have routed things differently.
The other thing I'd love opinions on is paperwork. My county wanted three line diagrams, spec sheets for every component, even the mounting hardware. Took me two resubmittals to get it right. Did anyone else find the permitting harder than the actual install? Because honestly, climbing around on the roof in Florida summer heat was not the fun part, but the paperwork nearly broke me.
Not looking for the one right answer here, just want to hear how other DIY folks approached it and if you'd change anything now that it's running.