Power mains question: wire gauge

Dec 28, 2012 170 Replies

I didn't get the shift key pressed for the '#', but you knew that.

I guess anything can happen if you don't know what you're doing.

#12 (or

Then

it,

You

Yes.

Good God, you're pissy tonight. Take a pain killer and come back tomorrow!

Clueless.

I'd run 12AWG. It's a *lot* cheaper and will handle the load quite well.

It *rarely* does.

Yawn. You clearly overbuild everything, maybe because it's fun. However, it's *NOT* economical. Running a separate service for each tool (which is rarely even needed) is almost always cheaper.

Yawn.

I've not had much success with pulling new conductors in a cable with existing conductors. I found that the pull string doesn't lay nicely along side the conductor when installed, instead threading itself through the conductors. When it comes time to use the pull thread, the new conductors intertwine with the existing ones... a real mess.

Unless there's a trick to this that I've not heard about...

Thanks.

That's been my (limited) experience too.

Those things can happen but they have never happened to me if I was the one to run the wire and string.

Sigh. He's RETIRED. He built more than cabinets in his home shop. He has more than a nailer that needs compressed air in his shop. Go hump someone else's leg.

Then

it,

just to

Hell, we had six breaker boxes on the production floor at Microdyne for outlets for workbenches on a 200' * 190' production area. Then there was a power room with over 200 breakers for the other equipment.

Certainly that you've never worked in a machine shop?

You end up living in Alabama.

Then

it,

just to

Wrong, of course. There was one panel with a separate drop for each tool.

BTW, did the OP specify a machine shop? I don't remember that part.

#12 (or

Then

You

to it,

You

I don't take pain killers. None are prescribed.

I'd run the 10. I have 14, 12 & 10 on hand. I use 14 for light circuits, 12 for most 120V outlets, and 10 for the longer or heavier loads. There is 75 feet of #6 run to the well house.

In your limited experience.

You cut lots of corners and do everything on the edge of failure. Labor cost more than the materials, so the difference in the total build is small.

Of course you yawn. That's a requirement of the initial specs for public buildings, everywhere that I've lived & worked.

So it's not a "machine shop". Giggle. Get real, Michael.

You're the one doing the humping, Michael.

Not anymore. He worked for a schoolboard in their maintenece complex. They had a MACHINE SHOP, cabinet shop and garage where they did maintenece on all their vehicles. They had in house support for everything except new costruction & roofing

Keep showing your petty ignorance.

You did, and you decided to move there so you're the fool.

Then

You

to it,

just to

expensive

of

That must have been a tiny shop.

He said he was going to suggest it to the owner, so who knows.

Some people also pull THHN or CAT5 off the box spool the same way, also makes a mess. It takes more time but if you spiral (cable) your bundle the pull cord will not get mixed. Never has for me.

Then

You

to it,

just to

expensive

of

Hardly, but you're dreaming again.

So why not 500KV? You never know?

Still dry humping? Come on, Michael. Drop it already.

More dry humping from Michael. I hope you feel better soon.

Join the Discussion

Have something to add? Share your thoughts — no account required.

Didn't find your answer?

Ask the community — no account required